Sunday, February 11, 2007

The scratch coat and brown coat stucco was finished this week. It's looking more like a 'real house' ! Now we'll wait about three weeks for it to dry out before the final color coat is applied.
Steve finished installing some sound proofing insulation in the family room. The drywall materials will be delivered Monday and they should start hanging it Tuesday.


We decided on the shop/garage shower tile and the installer should be here this week to lay it. We bought an under-the-counter refrigerator for the office, now the cabinet maker can now design the remainder of the counters for Steve's office.